Time & Work Problems for SBI Clerk 2016 Prelims - Set 1


Hello and welcome to ExamPundit. Here is a set of Quantitative Aptitude Quiz based on Time & Work for SBI Junior Associates Prelims 2016. 


Rules:


Post answers according to the following format(s)
1-2
2-3
3-4
Or
12345
54213
In case the options are ABCD, use the Appropriate Options.


Do Not Rectify anyone.


If you have any doubt regarding any question of the quiz, kindly ask after the quiz is over i.e answers given.


DO NOT GOOGLE ANSWERS!! IT WILL HAMPER YOUR PREPARATION


Do Not CHAT here. If you have any query, use today’s Ask The Mentor Page.


At least 10 Attempts for Scores.

Exampundit.in reserves the right to choose winner or give scores.


1. Ramya can do a piece of work in 40 days. Sunaina is 25% more efficient than Ramya. The number of days taken by Sunaina to do the same piece of work is
1) 24 days
2) 28 days
3) 32 days
4) 35 days


2. A can do a work in 12 days and B in 15 days. If they work on it together for 6 days, then the fraction of the work that is left is
1) ¼
2) 1/5
3) 1/10
4) 1/12


3. A alone can complete work in 15 days and B alone in 20 days. Starting with A, the work on alternate days. The total work will be completed in
1) 17 days
2) 16 days
3) 14 days
4) 13 days


4. A alone can complete a work in 12 days and B alone in 48 days. Starting with B, they work on alternate days. The total work will be completed in
1) 18 days
 2) 19 days
3) 19 ½ days
4) Data insufficient


5. 4 men can do a piece of work in 10 days, 2 women can do it in 15 days and 5 children can do it in 12 days. In how many days can 8 men, 5 women and 15 children together complete the piece of work?
1) 2 days
2) 3 days
3) 4 days
4) None of these


6. 48 workers can reap a field in 9 days. If the work is to be completed in 6 days, the extra workers required are
1) 36
2) 32
3) 24
4) 22


Sponsored






7. 4 men and 6 boys can do a piece of work in 8 days and 6 men and 4 boys can do it in 7 days. If the daily wages of a boy be Rs. 20, what will be the weekly wages of a man?
1) Rs. 280
2) Rs. 275
3) Rs. 270
4) Rs. 265


8. A is thrice as good a workman as B and is therefore able to finish a piece of work in 30 days less than B. Find the time in which they can do it working together.
1) 45 days
2) 11¼ days
3) 15 days
4) 22½ days



9. A takes twice as much time as B to do a work. Working together the work is completed in 8 days. A can do the work alone in
1) 24 days
2) 12 days
3) 16 days
4) 28 days


10. A and B can finish a work in 10 days while B and C can do it in 18 days. A started the work, worked for 5 days, then B worked for 10 days and the remaining work was finished by C in 15 days. In how many days could C alone have finished the whole work ?
1) 30 days
2) 15 days
3) 45 days
4) 24 days


11. A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
1) 11 days
2) 13 days
3) 20 3/17 days
4) None of these


12. Sanket and Ratul can complete a work in 5 days and 15 days respectively. They both work for one day and then Sanket leaves. In how many days will the remaining work be completed by Ratul ?
1) 11 days
2) 12 days
3) 15 days
4) 8 days


Winners:

  • bacha party - 12/12
  • Chitrarth - 11/11
  • Achillish - 11/12





Regards



Team ExamPundit